480
- 6 Hands ( Instalation/ Deinstalation )
- 1 electrician /nonstop operating
- 1 production manager (Dome) / nonstop operating / nonstop check weather forecasts (wind, rain) / wather for weights
- 2 people - security at a time between instalation/ deinstalation/ event
- 3 - 4 people – security at a time of event ( it depend on crowd around)
- 20 meters (2 meters high)/ white covered/ of fences for technical area (fans, diesel generator etc) !!!!
- minimum 20-30 meters (1 meter high) crowd control fences - Main Doors
- You can have the fences around the Dome ( 1 meter), minimum 1,5 m from inflatable wall
- Trussing and whole idoor equipment must to 40-50cm from the inflatable wall
- minimum area for instalation / deinstalation: 25 x 25 m in the undeveloped location (park, stadion etc.), 30 x 30 m in built-up location (city)
- Electric power 6x 1500 W / 220 V (for 6 blowers)
- Cables (for blowers and emergency light )
- Backup diesel generator 6000 W ( for 3 blowers)!!! Minimum!!!
- 11 m3 of water + Water hose (with regulation) with a range around the Dome + diameter (type)of ventil TBC
- 1 Forklift (manual forklift suffiecent) for un/loading, mooving and seting doors and Dome etc. (only one!!!)
- Hight pressure water cleaning system (backup)
- Single-use gloves, shoe covers (for 8 persons)
- production tools
- 5m ladder or stepladder
- broom and shovel